Region | Province | Subprojects | No. of Proponent Groups | Total Cost |
---|---|---|---|---|
Region 13 | Agusan del Norte | 1 Start-up | 8 | 14,715,652.05 |
Region 13 | Agusan del Norte | 1 Upgrading / Expansion | 1 | 17,443,823.91 |
Region 13 | Agusan del Norte | 2 Upgrading / Expansion | 6 | 19,774,831 |
Region 13 | Agusan del Sur | 2 Upgrading / Expansion | 2 | 12,432,508 |
Region 13 | Agusan del Sur | 1 Restoration / Rehabilitation | 1 | 519,875.61 |
Region 13 | Agusan del Sur | 1 Upgrading / Expansion | 1 | 16,507,096.30 |
Region 13 | Dinagat Islands | 3 Start-up | 14 | 14,830,604.66 |
Region 13 | Surigao del Norte | 1 Start-up | 1 | 2,760,500 |
Region 13 | Surigao del Norte | 1 Upgrading / Expansion | 1 | 10,501,000 |
Region 13 | Surigao del Sur | 3 Upgrading / Expansion | 7 | 20,945,630.21 |
Region 13 | Surigao del Sur | 4 Upgrading / Expansion | 8 | 116,202,182.28 |
Total | 246,633,704.02 |