Subproject by Type as of July 01, 2022
Type of Subprojects |
Number of Subprojects |
Beneficiaries |
Subproject Cost |
LP |
GEF |
GOP |
LGU Equity |
Total |
Start-up | 183 | Proponent Groups (366) Members (56,944) | 998,843,825.59 | 0 | 332,947,941.86 | 332,947,941.86 | 1,664,739,709.31 |
Upgrading / Expansion | 117 | Proponent Groups (289) Members (48,495) | 983,991,278.93 | 0 | 327,997,092.93 | 327,997,092.93 | 1,639,985,464.79 |
Restoration / Rehabilitation | 401 | Proponent Groups (443) Members (52,878) | 224,197,809.22 | 0 | 74,732,603.07 | 74,732,603.07 | 373,663,015.36 |
Global Environmental Facility (GEF) | 25 | Proponent Groups (31) Members (1,716) | 0 | 29,698,526.29 | 0 | 7,424,631.58 | 37,123,157.87 |
Total | 726 | | 2,207,032,913.74 | 29,698,526.29 | 735,677,637.86 | 743,102,269.44 | 3,715,511,347.33 |