Subproject by Stage as of July 14, 2024

ยป Start-up

Stages of Subprojects Number of
Subprojects
Subproject Cost
LP GEF GOP LGU Equity Total
Approved Subprojects1991,028,131,101.240342,710,367.09342,710,367.091,713,551,835.39
Completed (100%)148732,536,766.960244,178,922.31244,178,922.311,220,894,611.58
Start-upProponent Groups  (292)
Members  (47,263)
148732,536,766.960244,178,922.31244,178,922.311,220,894,611.58
Under Implementation43258,536,695.45086,178,898.5086,178,898.50430,894,492.42
Fifty percent and above progress33184,015,902.63061,338,634.2261,338,634.22306,693,171.04
Start-upProponent Groups  (102)
Members  (8,185)
33184,015,902.63061,338,634.2261,338,634.22306,693,171.04
Less than fifty percent progress1074,520,792.82024,840,264.2824,840,264.28124,201,321.38
Start-upProponent Groups  (20)
Members  (2,424)
1074,520,792.82024,840,264.2824,840,264.28124,201,321.38
With NOL 2000000
Under Procurement837,057,638.83012,352,546.2812,352,546.2861,762,731.39
With NOL 1837,057,638.83012,352,546.2812,352,546.2861,762,731.39
Start-upProponent Groups  (12)
Members  (3,967)
837,057,638.83012,352,546.2812,352,546.2861,762,731.39
Pipelined Subprojects525,842,704.4008,614,234.808,614,234.8043,071,174
Endorsed for Issuance of NOL 1000000
Approved by RPAB000000
Business Plan Preparation525,842,704.4008,614,234.808,614,234.8043,071,174
Start-upProponent Groups  (5)
Members  (40)
525,842,704.4008,614,234.808,614,234.8043,071,174
Total2041,053,973,805.640351,324,601.89351,324,601.891,756,623,009.42