Subproject by Stage as of December 17, 2024

ยป Start-up

Stages of Subprojects Number of
Subprojects
Subproject Cost
LP GEF GOP LGU Equity Total
Approved Subprojects1981,024,707,447.620341,569,149.22341,569,149.221,707,845,746.04
Completed (100%)158792,010,717.650264,003,572.55264,003,572.551,320,017,862.74
Start-upProponent Groups  (317)
Members  (50,301)
158792,010,717.650264,003,572.55264,003,572.551,320,017,862.74
Under Implementation36204,235,665.48068,078,555.1768,078,555.17340,392,775.82
Fifty percent and above progress33187,677,624.29062,559,208.1162,559,208.11312,796,040.50
Start-upProponent Groups  (97)
Members  (7,933)
33187,677,624.29062,559,208.1162,559,208.11312,796,040.50
Less than fifty percent progress316,558,041.1905,519,347.065,519,347.0627,596,735.32
Start-upProponent Groups  (3)
Members  (209)
316,558,041.1905,519,347.065,519,347.0627,596,735.32
With NOL 2000000
Under Procurement428,461,064.4909,487,021.509,487,021.5047,435,107.48
With NOL 1428,461,064.4909,487,021.509,487,021.5047,435,107.48
Start-upProponent Groups  (8)
Members  (3,854)
428,461,064.4909,487,021.509,487,021.5047,435,107.48
Pipelined Subprojects313,197,58504,399,1954,399,19521,995,975
Endorsed for Issuance of NOL 1000000
Approved by RPAB000000
Business Plan Preparation313,197,58504,399,1954,399,19521,995,975
Start-upProponent Groups  (3)
Members  (40)
313,197,58504,399,1954,399,19521,995,975
Total2011,037,905,032.620345,968,344.22345,968,344.221,729,841,721.06