Stages of Subprojects | Number of Subprojects |
Subproject Cost | |||||||
---|---|---|---|---|---|---|---|---|---|
LP | GEF | GOP | LGU Equity | Total | |||||
Approved Subprojects | 198 | 1,024,368,673.80 | 0 | 341,456,224.61 | 341,456,224.61 | 1,707,281,123 | |||
Completed (100%) | 184 | 932,911,166.34 | 0 | 310,970,388.79 | 310,970,388.79 | 1,554,851,943.90 | |||
Start-upProponent Groups (373) Members (54,959) | 184 | 932,911,166.34 | 0 | 310,970,388.79 | 310,970,388.79 | 1,554,851,943.90 | |||
Under Implementation | 10 | 62,996,442.97 | 0 | 20,998,814.32 | 20,998,814.32 | 104,994,071.62 | |||
Fifty percent and above progress | 9 | 58,481,455.75 | 0 | 19,493,818.58 | 19,493,818.58 | 97,469,092.92 | |||
Start-upProponent Groups (43) Members (3,330) | 9 | 58,481,455.75 | 0 | 19,493,818.58 | 19,493,818.58 | 97,469,092.92 | |||
Less than fifty percent progress | 1 | 4,514,987.22 | 0 | 1,504,995.74 | 1,504,995.74 | 7,524,978.70 | |||
Start-upProponent Group (1) Members (154) | 1 | 4,514,987.22 | 0 | 1,504,995.74 | 1,504,995.74 | 7,524,978.70 | |||
With NOL 2 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Under Procurement | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
With NOL 1 | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
Start-upProponent Groups (8) Members (3,854) | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
Pipelined Subprojects | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Endorsed for Issuance of NOL 1 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Approved by RPAB | 0 | 0 | 0 | 0 | 0 | 0 | |||
Business Plan Preparation | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Start-upProponent Groups (3) Members (40) | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Total | 201 | 1,037,566,258.80 | 0 | 345,855,419.61 | 345,855,419.61 | 1,729,277,098.02 |