Stages of Subprojects | Number of Subprojects |
Subproject Cost | |||||||
---|---|---|---|---|---|---|---|---|---|
LP | GEF | GOP | LGU Equity | Total | |||||
Approved Subprojects | 198 | 1,024,707,447.62 | 0 | 341,569,149.22 | 341,569,149.22 | 1,707,845,746.04 | |||
Completed (100%) | 158 | 792,010,717.65 | 0 | 264,003,572.55 | 264,003,572.55 | 1,320,017,862.74 | |||
Start-upProponent Groups (317) Members (50,301) | 158 | 792,010,717.65 | 0 | 264,003,572.55 | 264,003,572.55 | 1,320,017,862.74 | |||
Under Implementation | 36 | 204,235,665.48 | 0 | 68,078,555.17 | 68,078,555.17 | 340,392,775.82 | |||
Fifty percent and above progress | 33 | 187,677,624.29 | 0 | 62,559,208.11 | 62,559,208.11 | 312,796,040.50 | |||
Start-upProponent Groups (97) Members (7,933) | 33 | 187,677,624.29 | 0 | 62,559,208.11 | 62,559,208.11 | 312,796,040.50 | |||
Less than fifty percent progress | 3 | 16,558,041.19 | 0 | 5,519,347.06 | 5,519,347.06 | 27,596,735.32 | |||
Start-upProponent Groups (3) Members (209) | 3 | 16,558,041.19 | 0 | 5,519,347.06 | 5,519,347.06 | 27,596,735.32 | |||
With NOL 2 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Under Procurement | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
With NOL 1 | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
Start-upProponent Groups (8) Members (3,854) | 4 | 28,461,064.49 | 0 | 9,487,021.50 | 9,487,021.50 | 47,435,107.48 | |||
Pipelined Subprojects | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Endorsed for Issuance of NOL 1 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Approved by RPAB | 0 | 0 | 0 | 0 | 0 | 0 | |||
Business Plan Preparation | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Start-upProponent Groups (3) Members (40) | 3 | 13,197,585 | 0 | 4,399,195 | 4,399,195 | 21,995,975 | |||
Total | 201 | 1,037,905,032.62 | 0 | 345,968,344.22 | 345,968,344.22 | 1,729,841,721.06 |