Subproject by Stage as of May 07, 2025

ยป Start-up

Stages of Subprojects Number of
Subprojects
Subproject Cost
LP GEF GOP LGU Equity Total
Approved Subprojects1981,024,368,673.800341,456,224.61341,456,224.611,707,281,123
Completed (100%)184932,911,166.340310,970,388.79310,970,388.791,554,851,943.90
Start-upProponent Groups  (373)
Members  (54,959)
184932,911,166.340310,970,388.79310,970,388.791,554,851,943.90
Under Implementation1062,996,442.97020,998,814.3220,998,814.32104,994,071.62
Fifty percent and above progress958,481,455.75019,493,818.5819,493,818.5897,469,092.92
Start-upProponent Groups  (43)
Members  (3,330)
958,481,455.75019,493,818.5819,493,818.5897,469,092.92
Less than fifty percent progress14,514,987.2201,504,995.741,504,995.747,524,978.70
Start-upProponent Group  (1)
Members  (154)
14,514,987.2201,504,995.741,504,995.747,524,978.70
With NOL 2000000
Under Procurement428,461,064.4909,487,021.509,487,021.5047,435,107.48
With NOL 1428,461,064.4909,487,021.509,487,021.5047,435,107.48
Start-upProponent Groups  (8)
Members  (3,854)
428,461,064.4909,487,021.509,487,021.5047,435,107.48
Pipelined Subprojects313,197,58504,399,1954,399,19521,995,975
Endorsed for Issuance of NOL 1000000
Approved by RPAB000000
Business Plan Preparation313,197,58504,399,1954,399,19521,995,975
Start-upProponent Groups  (3)
Members  (40)
313,197,58504,399,1954,399,19521,995,975
Total2011,037,566,258.800345,855,419.61345,855,419.611,729,277,098.02