Subproject by Stage as of March 19, 2024

Stages of SubprojectsNumber of SubprojectsLoan ProceedsGovernment of the PhilippinesLocal Government Unit EquityEuropean Union GrantTotal
Approved Subprojects60432,970,596,527.014,214,370,448.094,214,370,448.09744,367,055.6642,143,704,478.15
Completed (100%)47323,291,966,845.142,917,895,639.182,917,895,639.1851,198,266.4829,178,956,389.45
Farm to Market Road (FMR)1,781.33 Kilometers26117,759,669,464.952,223,477,495.672,223,477,495.6728,150,50022,234,774,956.29
FMR with Bridge266.57 Kilometers
1,740.34 Linear Meters
293,525,625,207.34440,703,150.93440,703,150.9304,407,031,509.20
Bridge387.10 Linear Meters6188,652,108.4623,581,513.5723,581,513.570235,815,135.60
Communal Irrigation System (CIS)2,816.26 Hectares24360,703,673.3345,087,959.2045,087,959.200450,879,591.73
Potable Water Supply (PWS) Level 29,484 Number of Households26133,571,087.0117,256,351.4817,256,351.484,479,724.67172,563,514.64
Others94,279.55 Square Meters1271,323,745,304.05167,789,168.33167,789,168.3318,568,041.811,677,891,682.52
Under Implementation1299,424,788,347.611,264,744,642.131,264,744,642.13693,168,789.1812,647,446,420.88
Fifty percent and above progress656,048,132,231.28799,601,604.55799,601,604.55348,680,605.017,996,016,045.26
Farm to Market Road (FMR)281.56 Kilometers313,747,529,697.21495,329,128.46495,329,128.46215,103,330.594,953,291,284.72
FMR with Bridge81.76 Kilometers
534.50 Linear Meters
91,391,505,261184,168,467.09184,168,467.0981,842,475.521,841,684,670.70
Bridge210.90 Linear Meters2132,518,306.4516,564,788.3016,564,788.300165,647,883.05
Potable Water Supply (PWS) Level 220,691 Number of Households9574,722,830.0275,958,546.2375,958,546.2332,945,539.85759,585,462.33
Others16,755.43 Square Meters14201,856,136.6027,580,674.4727,580,674.4718,789,259.05275,806,744.59
Less than fifty percent progress633,338,656,125.79460,393,038.76460,393,038.76344,488,184.174,603,930,387.45
Farm to Market Road (FMR)166.94 Kilometers261,862,258,867.89262,503,678.62262,503,678.62237,770,561.012,625,036,786.14
FMR with Bridge24.88 Kilometers
130 Linear Meters
3423,261,183.6852,907,647.9652,907,647.960529,076,479.60
Bridge60 Linear Meters136,595,2004,574,4004,574,400045,744,000
Potable Water Supply (PWS) Level 211,474 Number of Households8249,336,060.4943,916,649.4243,916,649.42101,997,134.93439,166,494.26
Others40,053.99 Square Meters25767,204,813.7396,490,662.7696,490,662.764,720,488.23964,906,627.48
With NOL 2137,999,990.544,749,998.824,749,998.82047,499,988.17
Others2,000 Square Meters137,999,990.544,749,998.824,749,998.82047,499,988.18
Under Procurement2253,841,334.2631,730,166.7831,730,166.780317,301,667.82
With NOL 12253,841,334.2631,730,166.7831,730,166.780317,301,667.82
Farm to Market Road (FMR)14.82 Kilometers2253,841,334.2631,730,166.7831,730,166.780317,301,667.82
Pipelined Subprojects49744,737,498,587.785,602,726,514.945,602,726,514.9484,313,531.9156,027,265,149.62
Endorsed for Issuance of NOL 1000000
Approved by RPAB20416,406,541,707.622,061,356,904.912,061,356,904.9184,313,531.9120,613,569,049.44
Farm to Market Road (FMR)512.63 Kilometers687,657,402,014.29967,092,407.84967,092,407.8479,337,248.729,670,924,078.69
FMR with Bridge237.96 Kilometers
945.20 Linear Meters
254,521,513,793.92565,189,224.24565,189,224.2405,651,892,242.40
Bridge30 Linear Meters130,379,2003,797,4003,797,400037,974,000
Communal Irrigation System (CIS)350 Hectares226,685,0003,747,0003,747,0003,291,00037,470,000
Potable Water Supply (PWS) Level 220,487 Number of Households28936,502,689.09117,062,836.14117,062,836.1401,170,628,361.37
Others124,766.10 Square Meters803,234,059,010.32404,468,036.69404,468,036.691,685,283.194,044,680,366.89
Under FS / DED Preparation22318,742,101,645.652,342,762,705.712,342,762,705.71023,427,627,057.06
Farm to Market Road (FMR)668.63 Kilometers8410,687,226,715.761,335,903,339.481,335,903,339.48013,359,033,394.72
FMR with Bridge206.83 Kilometers
1,307.60 Linear Meters
245,082,106,625.89635,263,328.23635,263,328.2306,352,633,282.35
Bridge615 Linear Meters5349,520,00043,690,00043,690,0000436,900,000
Communal Irrigation System (CIS)840.69 Hectares19275,493,696.6534,436,712.0834,436,712.080344,367,120.81
Potable Water Supply (PWS) Level 217,589 Number of Households26872,665,977.32109,083,247.16109,083,247.1601,090,832,471.64
Others45,598.23 Square Meters651,475,088,630.03184,386,078.76184,386,078.7601,843,860,787.55
Under Validation709,588,855,234.511,198,606,904.321,198,606,904.32011,986,069,043.12
Farm to Market Road (FMR)292.15 Kilometers446,586,194,071.63823,274,258.96823,274,258.9608,232,742,589.55
FMR with Bridge42.83 Kilometers
30 Linear Meters
132,515,182,811.79314,397,851.47314,397,851.4703,143,978,514.73
Bridge25 Linear Meters120,000,0002,500,0002,500,000025,000,000
Communal Irrigation System (CIS)22.40 Hectares213,088,0001,636,0001,636,000016,360,000
Potable Water Supply (PWS) Level 22,899 Number of Households3250,299,973.5631,287,496.7031,287,496.700312,874,966.96
Others7204,090,377.5325,511,297.1925,511,297.190255,112,971.91
Total110177,708,095,114.799,817,096,963.039,817,096,963.03828,680,587.5798,170,969,628.42
Status Scope
Completed (100%) Covers subprojects with 100% physical progress (validated by the RPCOs / PSOs, with Joint Inpsection Team Inspection Report).
Less than fifty percent progress Covers subprojects that are (i) issued with Notice to Proceed (NTP) and (ii) undergoring construction activities (execution of contract) with physical progress below 50%.
Fifty percent and above progress Covers subprojects that are undergoring construction activities (execution of contract) with physical progress ranging from 50% to 99%.
With NOL 1 Covers subprojects issued with No Objection Letter (NOL) 1 allowing the proponent LGUs to proceed with procurement process.
With NOL 2 Covers subprojects issued with No Objection Letter (NOL) 2 allowing the proponent LGUs to proceed with awarding of contracts to the winning bidders.
Endorsed for Issuance of NOL 1 Covers subprojects under review by the PSO / NPCO for issuance of NOL 1
Approved by RPAB (for submission to the PSO for review / endorsement to the NPCO for NOL 1) Covers subprojects already approved by the RPAB that are (i) undergoing compliance with the conditions required by the RPAB prior to endorsement for NOL 1; and (ii) ready for endorsement to the PSO for review / endorsement to the NPCO for NOL 1.
Under FS / DED Preparation Covers subprojects that are (i) undergoing preparation of feasibility studies (FS), detailed engineering designs (DED), bidding documents and others required for approval; (ii) with draft FS (including DED, bidding documents, safeguards compliance documents, etc.) being reviewed by the RPCOs / PSOs prior to review / approval by the Regional Project Advisory Boards (RPAB); and (iii) For review / under review by the RPCOs, PSOs and NPCO for issuance of No Objection Letter (NOL) 1
Under Validation Covers subprojects that are (i) already scheduled for validation activity and (ii) already validated but pending submission of the "Validation Report" by the Regional Project Coordination Office (RPCO) I-BUILD Unit.