Subproject by Stage as of July 01, 2022

Stages of SubprojectsNumber of SubprojectsLoan ProceedsGovernment of the PhilippinesLocal Government Unit EquityTotal
Approved Subprojects53831,425,539,060.413,928,192,382.783,928,192,382.7839,281,923,825.46
Completed (100%)39516,435,040,958.582,054,380,120.012,054,380,120.0120,543,801,198.20
Farm to Market Road (FMR)1,388.27 Kilometers22112,884,922,030.131,610,615,253.771,610,615,253.7716,106,152,537.66
FMR with Bridge185.95 Kilometers
994.40 Linear Meters
182,213,554,107.93276,694,263.49276,694,263.492,766,942,634.91
Bridge267 Linear Meters5127,615,122.6215,951,890.3315,951,890.33159,518,903.27
Communal Irrigation System (CIS)2,816.26 Hectares24360,703,673.3345,087,959.1745,087,959.17450,879,591.66
Potable Water Supply (PWS) Level 29,574 Number of Households21104,360,848.9313,045,106.1213,045,106.12130,451,061.16
Others76,797.55 Square Meters106743,885,175.6392,985,646.9592,985,646.95929,856,469.54
Under Implementation789,144,676,302.841,143,084,537.891,143,084,537.8911,430,845,378.54
Fifty percent and above progress465,581,437,086.99697,679,635.88697,679,635.886,976,796,358.74
Farm to Market Road (FMR)332.28 Kilometers303,894,135,919.15486,766,989.89486,766,989.894,867,669,898.94
FMR with Bridge88.97 Kilometers
476.46 Linear Meters
101,295,233,532.01161,904,191.50161,904,191.501,619,041,915.01
Bridge120 Linear Meters161,037,062.467,629,632.817,629,632.8176,296,328.08
Potable Water Supply (PWS) Level 26,650 Number of Households3185,868,610.4523,233,576.3123,233,576.31232,335,763.06
Others2,280 Square Meters2145,161,962.9218,145,245.3718,145,245.37181,452,453.65
Less than fifty percent progress283,049,714,022.63381,214,252.86381,214,252.863,812,142,528.28
Farm to Market Road (FMR)131.33 Kilometers151,670,130,739.03208,766,342.38208,766,342.382,087,663,423.79
FMR with Bridge64.09 Kilometers
163 Linear Meters
71,157,923,022.63144,740,377.83144,740,377.831,447,403,778.29
Bridge120.90 Linear Meters190,736,00011,342,00011,342,000113,420,000
Potable Water Supply (PWS) Level 24,952 Number of Households261,399,842.627,674,980.337,674,980.3376,749,803.27
Others1,368 Square Meters369,524,418.348,690,552.298,690,552.2986,905,522.93
With NOL 24513,525,193.2264,190,649.1564,190,649.15641,906,491.52
Farm to Market Road (FMR)19.31 Kilometers2256,754,40032,094,30032,094,300320,943,000
FMR with Bridge1.87 Kilometers
61.50 Linear Meters
1101,182,40012,647,80012,647,800126,478,000
Potable Water Supply (PWS) Level 24,342 Number of Households1155,588,393.2219,448,549.1519,448,549.15194,485,491.52
Under Procurement655,845,821,798.99730,727,724.88730,727,724.887,307,277,248.72
With NOL 1655,845,821,798.99730,727,724.88730,727,724.887,307,277,248.72
Farm to Market Road (FMR)306.18 Kilometers414,542,697,813.37567,837,226.67567,837,226.675,678,372,266.71
FMR with Bridge12.57 Kilometers
365 Linear Meters
3355,951,20044,493,90044,493,900444,939,000
Bridge150 Linear Meters282,633,60010,329,20010,329,200103,292,000
Potable Water Supply (PWS) Level 26,691 Number of Households2174,633,60021,829,20021,829,200218,292,000
Others26,159.75 Square Meters17689,905,585.6186,238,198.2086,238,198.20862,381,982.01
Pipelined Subprojects44228,384,733,262.103,548,091,657.753,548,091,657.7535,480,916,577.65
Endorsed for Issuance of NOL 100000
Approved by RPAB26118,172,753,741.172,271,594,217.642,271,594,217.6422,715,942,176.48
Farm to Market Road (FMR)522.52 Kilometers778,406,424,553.981,050,803,069.251,050,803,069.2510,508,030,692.48
FMR with Bridge247.56 Kilometers
1,030.20 Linear Meters
274,814,675,808.47601,834,476.06601,834,476.066,018,344,760.59
Bridge30 Linear Meters130,379,2003,797,4003,797,40037,974,000
Communal Irrigation System (CIS)350 Hectares229,976,0003,747,0003,747,00037,470,000
Potable Water Supply (PWS) Level 220,121 Number of Households401,185,371,065.30148,171,383.16148,171,383.161,481,713,831.63
Others151,645.95 Square Meters1143,705,927,113.42463,240,889.18463,240,889.184,632,408,891.78
Under FS / DED Preparation1689,571,541,146.931,196,442,643.361,196,442,643.3611,964,426,433.66
Farm to Market Road (FMR)487.43 Kilometers575,970,501,842.08746,312,730.26746,312,730.267,463,127,302.60
FMR with Bridge123.40 Kilometers
665 Linear Meters
131,897,469,440.54237,183,680.07237,183,680.072,371,836,800.67
Bridge105 Linear Meters196,000,00012,000,00012,000,000120,000,000
Communal Irrigation System (CIS)613 Hectares1347,386,416.655,923,302.085,923,302.0859,233,020.81
Potable Water Supply (PWS) Level 27,286 Number of Households22311,691,751.9038,961,468.9938,961,468.99389,614,689.87
Others49,767.57 Square Meters621,248,491,695.77156,061,461.97156,061,461.971,560,614,619.71
Under Validation13640,438,37480,054,796.7580,054,796.75800,547,967.51
Farm to Market Road (FMR)9.55 Kilometers4422,379,165.5952,797,395.7052,797,395.70527,973,956.99
Bridge25 Linear Meters120,000,0002,500,0002,500,00025,000,000
Communal Irrigation System (CIS)22.40 Hectares14,312,000539,000539,0005,390,000
Potable Water Supply (PWS) Level 2233 Number of Households29,059,973.571,132,496.701,132,496.7011,324,966.96
Others13,507.64 Square Meters5184,687,234.8523,085,904.3623,085,904.36230,859,043.56
Total98059,810,272,322.517,476,284,040.537,476,284,040.5374,762,840,403.57
Status Scope
Completed (100%) Covers subprojects with 100% physical progress (validated by the RPCOs / PSOs, with Joint Inpsection Team Inspection Report).
Less than fifty percent progress Covers subprojects that are (i) issued with Notice to Proceed (NTP) and (ii) undergoring construction activities (execution of contract) with physical progress below 50%.
Fifty percent and above progress Covers subprojects that are undergoring construction activities (execution of contract) with physical progress ranging from 50% to 99%.
With NOL 1 Covers subprojects issued with No Objection Letter (NOL) 1 allowing the proponent LGUs to proceed with procurement process.
With NOL 2 Covers subprojects issued with No Objection Letter (NOL) 2 allowing the proponent LGUs to proceed with awarding of contracts to the winning bidders.
Endorsed for Issuance of NOL 1 Covers subprojects under review by the PSO / NPCO for issuance of NOL 1
Approved by RPAB (for submission to the PSO for review / endorsement to the NPCO for NOL 1) Covers subprojects already approved by the RPAB that are (i) undergoing compliance with the conditions required by the RPAB prior to endorsement for NOL 1; and (ii) ready for endorsement to the PSO for review / endorsement to the NPCO for NOL 1.
Under FS / DED Preparation Covers subprojects that are (i) undergoing preparation of feasibility studies (FS), detailed engineering designs (DED), bidding documents and others required for approval; (ii) with draft FS (including DED, bidding documents, safeguards compliance documents, etc.) being reviewed by the RPCOs / PSOs prior to review / approval by the Regional Project Advisory Boards (RPAB); and (iii) For review / under review by the RPCOs, PSOs and NPCO for issuance of No Objection Letter (NOL) 1
Under Validation Covers subprojects that are (i) already scheduled for validation activity and (ii) already validated but pending submission of the "Validation Report" by the Regional Project Coordination Office (RPCO) I-BUILD Unit.