Subproject by Stage as of July 14, 2024

Stages of SubprojectsNumber of SubprojectsLoan ProceedsGovernment of the PhilippinesLocal Government Unit EquityEuropean Union GrantTotal
Approved Subprojects60332,864,681,704.384,201,131,095.294,201,131,095.29744,367,055.7842,011,310,949.99
Completed (100%)49123,733,548,301.762,979,653,742.462,979,653,742.46103,681,636.1129,796,537,422.23
Farm to Market Road (FMR)1,808.69 Kilometers26418,112,233,588.892,271,342,290.622,271,342,290.6258,504,735.6922,713,422,905.82
FMR with Bridge266.57 Kilometers
1,740.34 Linear Meters
293,525,625,207.34440,703,150.93440,703,150.9304,407,031,509.20
Bridge387.10 Linear Meters6188,652,108.4623,581,513.5723,581,513.570235,815,135.60
Communal Irrigation System (CIS)2,816.26 Hectares24360,703,673.3345,087,959.2045,087,959.200450,879,591.73
Potable Water Supply (PWS) Level 213,523 Number of Households31186,812,660.6524,848,855.6624,848,855.6611,978,184.52248,488,556.49
Others102,495.55 Square Meters1371,359,521,063.09174,089,972.48174,089,972.4833,198,715.901,740,899,723.95
Under Implementation1118,995,470,468.361,204,519,486.051,204,519,486.05640,685,419.6712,045,194,859.94
Fifty percent and above progress796,956,151,362.65929,692,965.76929,692,965.76481,392,363.279,296,929,657.31
Farm to Market Road (FMR)317.96 Kilometers414,243,370,738.42570,793,634.98570,793,634.98322,978,341.515,707,936,349.89
FMR with Bridge81.76 Kilometers
534.50 Linear Meters
91,391,505,261184,168,467.09184,168,467.0981,842,475.521,841,684,670.70
Bridge270.90 Linear Meters3169,113,506.4521,139,188.3021,139,188.300211,391,883.05
Potable Water Supply (PWS) Level 220,467 Number of Households9612,262,315.0884,994,348.5184,994,348.5167,692,473.05849,943,485.15
Others28,039.09 Square Meters17539,899,541.7068,597,326.8868,597,326.888,879,073.19685,973,268.65
Less than fifty percent progress312,001,319,115.17270,076,521.47270,076,521.47159,293,056.402,700,765,214.46
Farm to Market Road (FMR)102.47 Kilometers131,022,491,362.68140,254,084.66140,254,084.6699,541,314.521,402,540,846.52
FMR with Bridge24.67 Kilometers
142 Linear Meters
3423,261,183.6852,907,647.9652,907,647.960529,076,479.60
Potable Water Supply (PWS) Level 27,659 Number of Households3158,555,001.7927,288,342.9627,288,342.9659,751,741.88272,883,429.59
Others20,554.33 Square Meters12397,011,567.0249,626,445.8949,626,445.890496,264,458.80
With NOL 2137,999,990.544,749,998.824,749,998.82047,499,988.17
Others2,000 Square Meters137,999,990.544,749,998.824,749,998.82047,499,988.18
Under Procurement1135,662,934.2616,957,866.7816,957,866.780169,578,667.82
With NOL 11135,662,934.2616,957,866.7816,957,866.780169,578,667.82
Farm to Market Road (FMR)6.60 Kilometers1135,662,934.2616,957,866.7816,957,866.780169,578,667.82
Pipelined Subprojects46240,667,812,631.305,090,324,063.345,090,324,063.3454,779,875.5450,903,240,633.55
Endorsed for Issuance of NOL 1000000
Approved by RPAB18914,274,908,928.711,791,211,100.511,791,211,100.5154,779,875.5417,912,111,005.35
Farm to Market Road (FMR)485.47 Kilometers647,087,293,780.18892,137,171.54892,137,171.5449,803,592.358,921,371,715.61
FMR with Bridge203.54 Kilometers
927.20 Linear Meters
234,020,043,385.64502,505,423.20502,505,423.2005,025,054,232.04
Bridge30 Linear Meters130,379,2003,797,4003,797,400037,974,000
Communal Irrigation System (CIS)350 Hectares226,685,0003,747,0003,747,0003,291,00037,470,000
Potable Water Supply (PWS) Level 217,242 Number of Households26704,404,320.2988,050,540.0488,050,540.040880,505,400.37
Others116,353.34 Square Meters732,406,103,242.60300,973,565.73300,973,565.731,685,283.193,009,735,657.25
Under FS / DED Preparation21517,743,008,475.552,217,876,059.452,217,876,059.45022,178,760,594.43
Farm to Market Road (FMR)659.96 Kilometers8210,525,661,8591,315,707,732.381,315,707,732.38013,157,077,323.76
FMR with Bridge190.13 Kilometers
1,007.60 Linear Meters
224,586,402,064.03573,300,258573,300,25805,733,002,580.03
Bridge510 Linear Meters4253,520,00031,690,00031,690,0000316,900,000
Communal Irrigation System (CIS)840.69 Hectares19275,493,696.6534,436,712.0834,436,712.080344,367,120.81
Potable Water Supply (PWS) Level 217,589 Number of Households24659,167,960.1082,395,995.0182,395,995.010823,959,950.12
Others45,081.83 Square Meters641,442,762,895.77180,345,361.98180,345,361.9801,803,453,619.73
Under Validation588,649,895,227.041,081,236,903.381,081,236,903.38010,812,369,033.77
Farm to Market Road (FMR)260.20 Kilometers385,826,849,092.05728,356,136.51728,356,136.5107,283,561,365.07
FMR with Bridge42.83 Kilometers
30 Linear Meters
132,515,182,811.79314,397,851.47314,397,851.4703,143,978,514.73
Communal Irrigation System (CIS)22.40 Hectares213,088,0001,636,0001,636,000016,360,000
Potable Water Supply (PWS) Level 22,666 Number of Households1241,240,00030,155,00030,155,0000301,550,000
Others453,535,323.206,691,915.406,691,915.40066,919,154
Total106573,532,494,335.689,291,455,158.639,291,455,158.63799,146,931.3292,914,551,584.26
Status Scope
Completed (100%) Covers subprojects with 100% physical progress (validated by the RPCOs / PSOs, with Joint Inpsection Team Inspection Report).
Less than fifty percent progress Covers subprojects that are (i) issued with Notice to Proceed (NTP) and (ii) undergoring construction activities (execution of contract) with physical progress below 50%.
Fifty percent and above progress Covers subprojects that are undergoring construction activities (execution of contract) with physical progress ranging from 50% to 99%.
With NOL 1 Covers subprojects issued with No Objection Letter (NOL) 1 allowing the proponent LGUs to proceed with procurement process.
With NOL 2 Covers subprojects issued with No Objection Letter (NOL) 2 allowing the proponent LGUs to proceed with awarding of contracts to the winning bidders.
Endorsed for Issuance of NOL 1 Covers subprojects under review by the PSO / NPCO for issuance of NOL 1
Approved by RPAB (for submission to the PSO for review / endorsement to the NPCO for NOL 1) Covers subprojects already approved by the RPAB that are (i) undergoing compliance with the conditions required by the RPAB prior to endorsement for NOL 1; and (ii) ready for endorsement to the PSO for review / endorsement to the NPCO for NOL 1.
Under FS / DED Preparation Covers subprojects that are (i) undergoing preparation of feasibility studies (FS), detailed engineering designs (DED), bidding documents and others required for approval; (ii) with draft FS (including DED, bidding documents, safeguards compliance documents, etc.) being reviewed by the RPCOs / PSOs prior to review / approval by the Regional Project Advisory Boards (RPAB); and (iii) For review / under review by the RPCOs, PSOs and NPCO for issuance of No Objection Letter (NOL) 1
Under Validation Covers subprojects that are (i) already scheduled for validation activity and (ii) already validated but pending submission of the "Validation Report" by the Regional Project Coordination Office (RPCO) I-BUILD Unit.